Tomlin Drive, Margate
Council owned land to the rear of Tomlin Dr, Margate has been identified for redevelopment to provide additional affordable housing.
The proposal is that we will reconfigure the existing hardstanding, parking area, garages, bin stores and drying areas to provide twelve brand new family homes.
There will also be improved landscaping and the creation of a communal garden areas for the new build and existing Thanet District Council blocks at the site.
The redevelopment aims to regenerate the current site, improve the parking and landscaping, and enhance the area for existing residents.
Phases
Construction
Construction works for the Staner Court development will commence in phases. Key dates are as follows:
1. Pre-site mobilisation (19th August 2024):
- Site clearance
- Erection of hoarding and hera fencing
- Utility connections
- Pre-commencement planning condition works
2. Formal start on site (30th September 2024):
- WW Martin begins main construction works
3. Project completion (27th February 2026)
The total construction programme is scheduled to last 73 weeks from the formal start date to completion.