Council owned land to the rear of Staner Court, Ramsgate has been identified for redevelopment to provide additional affordable housing.

The proposal is that we will reconfigure the existing hardstanding, amenity space, garages and parking areas to provide eleven brand new family homes.

There will also be improved landscaping and the creation of a larger communal garden area for the existing Thanet District Council residents.

The redevelopment aims to regenerate the current site, adding to and enhancing the sustainable and cohesive community.    

You're viewing real-time data. Participant counts are continuously updated for administrators. Please note that regular users see cached data, which may result in slight differences in the numbers.
17 participants

Phases

Phases overview
Concept Design - Pre-planning
Concept design - review
Developed Design
Planning permission
Procuring a Main Contractor
Meet the Contractor
Construction

Construction

23 September 2024 - 22 January 2026

Construction works for the Staner Court development will commence in phases. Key dates are as follows:

1. Pre-site mobilisation (19th August 2024):

   - Site clearance

   - Erection of hoarding and hera fencing

   - Utility connections

   - Pre-commencement planning condition works


2. Formal start on site (23rd September 2024):

   - WW Martin begins main construction works


3. Project completion (22nd January 2026)


The total construction programme is scheduled to last 69 weeks from the formal start date to completion.